City of Elk Grove and D&S Development Partner on $26.4M Project
The Elk Grove City Council approved the sale of a 1.9 acre City-owned property at 9676 Railroad Street to D&S Development, a...
1430 Q - Construction updates
Third floor concrete was poured. The project is ready to start framing on top.
1430 Q - Construction updates
The second floor concrete was poured.
19J - Progress
Here's the current photo of construction status. The level 3 concrete is complete and ready to start light gauge metal stud wall...
1430 Q - Construction updates
Getting ready to pour concrete for the first floor.
1430 Q - Construction updates
Foundation concrete is poured.
1430 Q - Concrete mock-up
Board formed concrete mock-ups for ground floor level are reviewed.
1430 Q - Construction updates
Foundation rebars are getting installed this week. .
730 I Office building - Lobby Concept
HRGA is developing lobby design for D & S Development. Existing escalators will be replaced with new stair.
Warehouse adaptive use
HRGA is working on the new concept for the existing warehouse structure with D&S development. The first step is to upgrade structure to...